IMPLEMENTATION SCHEDULE:
i. Registration of Unit (EM-1) - One day.
ii. Loan Sanction (including TFR) -2 Months
iii. NOC-Pollution Control Board -1 Month
iv. Installation of machinery -1 Month
v. Power connection -1 Month
vi. Testing operation -1 Month
vii. Production -7 Month onwards.