project cost on fixed capital
| SI | Description | Rs.lakhs |
| 1 | Land | on lease |
| 2 | Civil works | on lease |
| 3 | plant machinery | 5.010 |
| 4 | Laboratory equipment | 0.500 |
| 5 | Transport vehicle | 1.800 |
| 6 | pollution control equipment | 0.000 |
| 7 | Energy conservation equipment | 0.000 |
| 8 | cost of power connection | 0.100 |
| 9 | cost of electrification | 0.250 |
| 10 | Erection and commissioning | 0.220 |
| 11 | cost of machinery spares | 0.100 |
| 12 | cost of the office equipment | 0.500 |
| 13 | Deposits if any | 0.200 |
| 14 | company formation expenses | 0.170 |
| 15 | Gestation period expenses | 0.500 |
| 16 | Sales tax registration expenses | 0.100 |
| 17 | Initial advertisement and publicity | 0.300 |
| 18 | Contingencies | 0.350 |
| 19 | Working capital margin money | 0.400 |
| 20 | Total fixed capital | 10.500 |