IMPLEMENTATION SCHEDULE

The major activities in the implementation of the project has been listed and the average time for implementation of the project is estimated at5 months:

Sl no Activity

Time in months

1 Preparation of project report 1
2 Registration and other formalities 1
3 Sanction of loan 2
4

plant and machinery procurement and installation

1
5 Electricity connection and installation 1
6 procurement of raw materials 1/2
7 Recruitment of staffs 1/2
8 commercial production 1

Many of the above activities shall be initiated concurrently and the production can be started from 5th month onwards.