IMPLEMENTATION SCHEDULE
The major activities in the implementation of the project has been listed and the average time for implementation of the project is estimated at5 months:
Sl no | Activity | Time in months |
1 | Preparation of project report | 1 |
2 | Registration and other formalities | 1 |
3 | Sanction of loan | 2 |
4 | plant and machinery procurement and installation |
1 |
5 | Electricity connection and installation | 1 |
6 | procurement of raw materials | 1/2 |
7 | Recruitment of staffs | 1/2 |
8 | commercial production | 1 |
Many of the above activities shall be initiated concurrently and the production can be started from 5th month onwards.