IMPLEMENTATION SCHEDULE
The major activities in the implementation of the project has been listed and the average time for implementation of the project is estimated at5 months:
| Sl no | Activity | Time in months |
| 1 | Preparation of project report | 1 |
| 2 | Registration and other formalities | 1 |
| 3 | Sanction of loan | 2 |
| 4 | plant and machinery procurement and installation |
1 |
| 5 | Electricity connection and installation | 1 |
| 6 | procurement of raw materials | 1/2 |
| 7 | Recruitment of staffs | 1/2 |
| 8 | commercial production | 1 |
Many of the above activities shall be initiated concurrently and the production can be started from 5th month onwards.